Thanks! My overall room dimensions are about 11' W x 15' D, projection screen, front speakers on a stage (filled with sand - thanks to the threads here on how to properly build a stage), one row of three seats about 11' from the screen.
I've done the mirror-method first reflection points for the front channels. Based on that, I need three panels on each side wall, although thanks to a wall switch on one side, and the location of a chair on the other side, two of those three panels will need to be custom sized, and I'd like both walls to match visually. So 2x4, 3.5x4, and 2x2.
For the screen wall, do I generally want to cover as much of that wall as possible? At least the bottom 4 feet of it? So that's 4 more custom panels (two on the bottom, one on each side).
What about behind the screen? I could at least put some 1" 703/705 behind there, if it makes a big difference (although I dread taking that screen down, for fear of screwing up the screen material in some freak slip of my hands/feet).
For the back wall, the door handles make 2x4x4" bass trap panels tough, so I'd need custom panels there as well (like 3'8"x2'x4").
For the rear corners, I can put 2x4x4" panels in the bottom, but I'd need custom ones for the rest of the wall (although my rear speakers might make that pointless, as I couldn't get a full 2' diagonal based on their location).
I'd really like to just buy from someone and get this done. But given the number of custom panels, it seems like this would be substantially cheaper to do it myself? I have budget, but I think we're approaching a 2x or 3x factor versus doing it myself, and I could use OC705 (it seems like most pre-built ones use a substitute, which I guess is okay, but why not use 705?). I can also custom make the rear corners to almost look like part of the room (put some baseboard on the bottom, maybe even a little shelf on top if I only do 4-feet high, cut the sides on an angle to butt up seamlessly with the walls, etc.).
Sorry for the rambling... I'm diving in head first, and circling in on exactly what my next step is. And I like to move fast, so I'd like to order something from somewhere (either pre-made, or the materials) by today or tomorrow.
What are all your thoughts on this?